The expansion will be built in four non-continuous phases with an estimated start of construction in 2023 and an estimated completion of the last phase in 2034.

Phase 1, which will be constructed between 2023 and 2024, consists of a new 12-story 154-key hotel building and a 575-space parking garage.

Phase 2, which is planned for 2028 through 2029, will add an 11-story 261-key hotel building, a 736-space parking garage, a conference center, and retail. 

Phase 3, which will rise between 2032 through 2034, contains a 12-story 235-unit hotel building, a 297-space parking garage, and retail. 

The last phase, which is also planned for 2032 through 2034, calls for a new two-story hotel lobby and 34-space parking deck.

A majority of the expansion project will be built on underutilized surface parking lots. Only one small two-story building will be demolished to make way for development.

Source Link

By gulfportsbest

Owner of the “Best of Gulfport Fl” which was built to help people connect with all the amazing services, restaurants, salons, bars and shopping venues in our local area. Get all your questions answered and stay up to date on all the cool things happening in our little paradise.

Leave a Reply

Your email address will not be published. Required fields are marked *